Yikes! Assuming I don't want the fight and expense of obtaining a second loan extension (and I don't!) then we have 57 days left to get the house in shape for a real live appraisal. 4.75% sure looks better on paper than the current 8.75%, and the sooner we finish construction, the sooner that happens. Texas Lending has tentatively extended that amount- assuming we don't wait too long and miss the current rates.
This week the masons were up on scaffolding working on the dry stack wall openings- one and a half to go, then a long smooth line to get to the top of the ceiling. And then....two columns at the front entry. And then....the floors. And then....at some point....the foundation veneer, the front walk way, and far, far away, a fire pit on the edge of the ridge below the hot tub. Right now I will settle for dry stack and floors.
The rest of the mesquite doors are FINALLY on site. They have been at the door place in Fort Wort wanting for us to be ready for them. After setting them all in the doorways, David gave Mike's guys a lesson on lining up the seams on door trims and set them to work. They are about half way done and have some of them stained as well.
The sun room siding is completed, stained and sealed. The metal for the remaining roof is on site and waiting for Mike.
58 days and counting. When I look at the six page TO DO list on my refrigerator I don't see any way possible for a timely completion. Then I remember it WILL get completed. In God's time. Just like everything else.